Image: FeaturedRatio: 16:9 (1200 x 675)Situation: Engineer and owner reviewing a printed snag list at the door of a new Dubai apartment, hands and paper in focus, no faces or unit number visibleTitle: Developer Snag Repair Timeline DubaiAlt text: Owner and engineer reviewing a snag list after handover
Owner and engineer reviewing a snag list after handover

How Long Does a Developer Have to Fix Snags in Dubai?

Handover and DLP5 min read

How long a developer has to fix snags in Dubai is set by your own contract, not by one fixed number that applies to every home. Your Sale and Purchase Agreement (SPA) and its defects liability terms say how long you have to report defects and may say how the developer must respond. Your job is to report every defect in writing, inside the defects liability period, and keep a record of each follow-up.

The short answerQuick answer
Where it's set
Your SPA and its defects liability terms
Reporting window
The defects liability period (DLP)
What you do
Report in writing, keep a dated log
If repairs stall
Chase in writing, then escalate formally

Which Clocks Decide How Long a Developer Has to Fix Snags?

Owners often mix up separate time limits. Keeping them apart makes it much easier to know whether a developer is late.

1. The DLP reporting window

The defects liability period is the window in which you can report defects for the developer to fix. Published guides commonly describe it as around 12 months for general defects, but the length that applies to you is the one written in your SPA. Check when your DLP expires so a defect is not reported too late.

2. The repair period

Reporting a defect inside the DLP is one thing; how fast it is fixed is another. Some contracts set a response or repair period, while others only say repairs will be made within a reasonable time. Whatever your SPA says is the deadline you can hold the developer to.

3. Longer liability for structural problems

Serious structural defects can fall under longer legal responsibility than the DLP. The rules here are legal, so if you suspect a structural problem, speak to a property lawyer rather than relying on a general guide.

Image: Internal 1 (in the "Which clocks decide" section)Ratio: 16:9 (1200 x 675)Situation: Simple designer-made diagram with three horizontal bars labelled "DLP reporting window", "Repair period in your SPA" and "Structural liability (ask a lawyer)", no numbers or datesTitle: Three Clocks for Snag RepairsAlt text: Diagram comparing the DLP reporting window, the repair period and structural liability
Diagram comparing the DLP reporting window, the repair period and structural liability
Three separate time limits: reporting, repairing and structural liability.

How Do You Find Your Deadline in Your SPA?

Open your SPA and any handover letter, then search for these words. Note the clause number and the exact wording for each.

  • "Defects liability" or "defects liability period": how long you can report defects, and when it starts.
  • "Rectification" or "remedy": whether there is a time limit for repairs.
  • "Notice": how defects must be reported, such as by email, portal or letter.
  • "Completion" or "handover date": the date the DLP is counted from.
  • "Common areas": whether shared-area defects go to the developer or the management company.

What Does a Reasonable Wait Look Like in Practice?

Where the SPA has no fixed repair period, what matters is that the developer acknowledges your report, books the work and then completes it. A report with photos, room locations and clear descriptions is easier for the developer's team to act on than a list of vague notes. Keep every exchange in writing so you can show what was reported and when.

Use a simple log like this for every defect:

ColumnWhat to record
DefectRoom, location and a short description
Date reportedThe date you sent it, and how
Developer referenceTicket or email reference number
PhotoBefore and after images
Follow-up datesEach reminder you sent
StatusOpen, booked, fixed or re-checked
Image: Internal 2 (in the "What a reasonable wait looks like" section)Ratio: 4:3 (1200 x 900)Situation: Screenshot of an anonymised defect log spreadsheet with dates, developer reference numbers and status columns, all names and unit numbers hiddenTitle: Snag Repair Evidence LogAlt text: Defect log showing report dates and developer references
Defect log showing report dates and developer references
A dated log is your evidence if repairs stall.

When and How Should You Escalate?

Escalate step by step, and keep each step in writing.

  1. Send a formal written notice.Attach the report and your log, and quote the SPA clause.
  2. Follow up with a clear date.Ask for a written repair schedule and a named contact.
  3. Talk it through.Many issues are settled by negotiating with the developer before any complaint.
  4. Raise a formal complaint.If repairs still stall, see how the RERA complaint process works. The regulator is part of the Dubai Land Department.

When to get legal advice

We document defects; we can't force a developer to act. If your SPA is unclear, the developer disputes a defect, or you suspect a structural problem, speak to a property lawyer.

Why Book a Final Check Before the DLP Ends?

Some defects only appear after months of use, such as cracks, damp or failing seals. A final inspection shortly before the period closes gives you one last dated report while the developer is still responsible. Dubshy's site engineers also re-check earlier repairs at the same visit. Read what a DLP inspection covers.

FAQs

What if the developer refuses to fix the issues?

Ask for the refusal in writing, with the reason. Compare it with your SPA and your inspection report. If the defect is reported within the DLP and the developer still declines, use the escalation steps in this guide, and get legal advice before taking formal action so your complaint is based on the right clause.

What happens if the developer doesn't fix snags on time?

First, check what "on time" means in your SPA: some set a repair period, others don't. Send a written reminder with a clear date, and record it in your log. If repairs still don't happen, the next steps are a formal notice and then a complaint through the official route.

When does the defects liability period end?

It ends on the date set by your SPA, counted from the start date the contract gives, often handover or completion. Published guides commonly describe the period as around 12 months for general defects, but always confirm the length and start date in your own contract before relying on them.

Should I keep using a defect after reporting it?

Use common sense. If the defect is a safety risk, such as an electrical fault or an active leak, stop using that item and tell the developer straight away in writing. For cosmetic defects, carry on as normal, but photograph them first so their condition at the time of reporting is on record.

Book a Final Check Before Your DLP Ends

Send us your handover date and DLP end date, and we will inspect, re-check earlier repairs and give you a dated report. Fees are quoted after a short scope call, with all costs listed upfront.